#JodhpurPhulera updates for September
Total cost about 1600 cr
Physical progress 22 & 26%
Till now 127 and 152 crore
Expenditure 12.23 & 10.08 cr
Earthwork...
more... 1 lakh cum
Remaining earthwork 12 lakh cum
Minor bridges completed 10 & 2
Remaining minor bridge 102
Major bridges 1
Ballast 7,000 and 10,000 cum
Remaining Ballast 5.3 lakh cum
Blanketing 21,000 & 6,700 cum
Remaining Blanketing 3 lakh 25000 cum